Topic: How many lm of brett high kerb per day< Next Oldest | Next Newest >
Constructascape
Offline

Apprentice




Group: Members
Posts: 3
Joined: Mar. 2015
Posted: 18 Dec. 2015,22:45 QUOTE

Evening all

I do a fair bit of paving and have obviously laid the high kerb before but i just cant work out how much i would get through in a day.

We have circa 135LM to do on a drive we are quoting. Mainly straight and slightly down hill in places.

What are your thoughts? Not looking for someone to price the job for me just another opinion.

Cheers
Back to top
Profile Personal Message 
lemoncurd1702
Offline

Ganger




Group: Members
Posts: 713
Joined: Oct. 2013
Posted: 19 Dec. 2015,08:06 QUOTE

I think the laying is the quickest part. It's the mixing, setting out and screeding the bed that takes the time.
Once that's achieved you should easily bang out 8-10 lm an hour plus time for haunching.

I would allow at least 3 days for 2 men with an already prepared concrete race possibly more when you consider the stacking out of the kerbs.


--------------
Cheers
Lemoncurd
Back to top
Profile Personal Message 
lutonlagerlout
Offline

Chief tea boy




Group: Moderator
Posts: 15151
Joined: Aug. 2006
Posted: 19 Dec. 2015,16:52 QUOTE

sounds about right LC
I would say depending on site etc that it might take 2 men 3 days
1 knocking up and loading out
the other setting out and laying
LLL


--------------
"what,you want paying today??"

YOUR TEXT GOES HERE
Back to top
Profile Personal Message MSN 
Constructascape
Offline

Apprentice




Group: Members
Posts: 3
Joined: Mar. 2015
Posted: 19 Dec. 2015,22:11 QUOTE

When you say screed out. What do you mean. I bed out as i lay them.

AS the drives a decent size i was intending on having 4 of us on it so we dont get stuck there for to long. Two skilled and two labourers. I was going to allow 3 days for us. But at 600 a day the cost mount up pretty quickly
Back to top
Profile Personal Message 
lemoncurd1702
Offline

Ganger




Group: Members
Posts: 713
Joined: Oct. 2013
Posted: 20 Dec. 2015,10:18 QUOTE

If you screed the bed its just a matter of plonking the kerbs down. Much easier than bashing them into a windrow of concrete where bashing a kerb in tends to alter the one next to it.

I lay a semi dry concrete mix and screed around 25mm of a semi dry sand/cement mix on top.
Level two  paving blocks a screeding bars (about 3m) length apart to form spot levels remove them and screed to the spots. 30 kerbs laid in no time.
Much easier to maintain levels particularly when dealing with curves and changing levels.


--------------
Cheers
Lemoncurd
Back to top
Profile Personal Message 
sy76uk
Offline

Ganger




Group: Members
Posts: 793
Joined: Feb. 2014
Posted: 22 Dec. 2015,20:27 QUOTE

Funnily enough I lay long runs of key kerbs in more or less the same way Mark.
I don't use the lean mix mortar and I'll use a couple of 300mm screed tubes so that when the kerbs are laid I can wet up the excess bed and haunch up.
When working on slopes I'll start from the bottom and work up to stop any of the kerbs from spacing out at the top.


--------------
http://sampaving.co.uk
Back to top
Profile Personal Message 
Thepinkpavingco
Offline

Ganger




Group: Members
Posts: 196
Joined: June 2011
Posted: 17 Jan. 2016,00:14 QUOTE

I can screed and lay about 180 units in a day. One man knocking up and me laying buttering up each one then my lad follows up pointing and haunching.

--------------
Think paving, think pink!
Back to top
Profile Personal Message 
Dave_L
Offline

Surfacing & Civils Contractor




Group: Moderator
Posts: 4729
Joined: July 2006
Posted: 24 Jan. 2016,16:23 QUOTE

Yep, screed the concrete and lay away, then with a bit of timber settle them down into the bed. Sorted :)

--------------
RW Gale Ltd - Civils & Surfacing Contractors based in Somerset

See what we get up to Our Facebook page
Back to top
Profile Personal Message 
7 replies since 18 Dec. 2015,22:45 < Next Oldest | Next Newest >

[ Track this topic :: Email this topic :: Print this topic ]

 
reply to topic start new topic
Quick Reply: How many lm of brett high kerb per day

Do you wish to enable your signature for this post?
Do you wish to enable emoticons for this post?
Track this topic
View All Emoticons
View iB Code


ruler

ruler