Posted: 27 Nov. 2019,13:30 QUOTE

Hi there,

I'm starting the process of building myself a timber framed workshop (approx. 3.5x2.5m).
The previous owners had a concrete slab patio laid on cement base with  bit of sand underneath.
The slabs lifted off the screed resonably easily and it appears pretty solid underneath.
There are some sections where the screed came up or there was no patio and so I plan to lay type 1 MOT to a dpeth of 75-100mm and then pour a 100m concrete slab to form my base.
Question is: could I lay the MOT around the existing screed, compact to level it with the screed and then pour the slab on top of all of it? So some areas will be slab on MOT, some areas will be slab on screed.
I don't have side access and so, if not cowboying it, I'd like to avoid hefting a load of old spoil through the house.

Many thanks in advance.
Back to top
Profile Personal Message 
Tony McC
Offline

Site Agent




Group: Moderator
Posts: 11082
Joined: July 2004
Posted: 27 Nov. 2019,14:04 QUOTE

I suspect the answer is probably "most likely!"

Will this workshop have a floor, or is the plan to use the exising and new base as the floor? If the latter, then you need to consider how you'll keep it watertight and allow for adequate drainage. However, if you're planning on having an internal floor, carried on joists of some kind, then the mixed-origin base will be no problem at all.


--------------
Site Agent - Pavingexpert
Back to top
Profile Personal Message WEB 
MrTickle
Offline

Apprentice




Group: Members
Posts: 2
Joined: Nov. 2019
Posted: 27 Nov. 2019,14:07 QUOTE

Thanks Tony.
The plan is to get the workshop semi-insulated so defintely a raised floor with joists sat on DPC strips.
Back to top
Profile Personal Message 
2 replies since 27 Nov. 2019,13:30 < Next Oldest | Next Newest >

[ Track this topic :: Email this topic :: Print this topic ]

 
reply to topic start new topic
Quick Reply: Sub-base for workshop

Do you wish to enable your signature for this post?
Do you wish to enable emoticons for this post?
Track this topic
View All Emoticons
View iB Code


ruler

ruler